EVENTS
Updated periodically, this Events Page showcases specific projects of our Building Campaign, both ongoing and completed works. We post each project's estimated funds needed, expected time of construction dates, status updates, and additional donation opportunities for our Building Fund.
Future Construction Coming Soon! Donate Now to help us build for the Greater Glory of God!
Engineering, Development, and Permitting
Funds: NEEDED!
ESTIMATED COST: $24,500
STATUS: In Progress - 58% of Goal met
DATES: June 2025 - TBA
Site Development Engineering and Permitting Phase will be completed with plans and specifications being submitted to the Gilchrist County Community Development Planning and Zoning Department. These Site Development Plans will include all the necessary planning, zoning and site engineering requirements, under Gilchrist County's Preliminary and Final Site Plan approval process. We are currently engaging a site engineer to prepare these plans. The anticipated cost and schedule for this work is ~$25,000 with an expected 8-month process to receive an approved site permit.



Site Prep
Architectural Design
Funds: ACQUIRED!
STATUS: COMPLETED
DATES: Feb 2025 - May 2025
​
​Our full Conceptual Design, with a Preliminary Building Construction matrix has been completed by Baker Architects', Lafayette, Co. In addition to providing the necessary Architectural floor plans and building elevations, Baker Architect's has provided us with three-dimensional (3-D) modeling of the building interior and exterior spaces, as well site plan overviews.




Back Property Fence
FUNDS: ACQUIRED!
COST: $3,328.84
CONSTRUCTION STATUS: COMPLETED
DATES: Oct/4/2024 - Oct/8/2024




Site Prep
Land Surveying
FUNDS: ACQUIRED!
Project claimed by Anonymous Donor!
COST: $1,854
CONSTRUCTION STATUS: COMPLETED
DATES: Aug/14/2024


Site Prep
Land Clearing For Monastery
FUNDS: ACQUIRED!
COST: $9,000
CONSTRUCTION STATUS: COMPLETED
DATES: May/11/2024 - May/16/2024




Front Property Fence
FUNDS: ACQUIRED!
Cost: $4,511.42
CONSTRUCTION: COMPLETED!
Dec/29/2023 - Dec/31/2023




Driveway Access
Front Clearing
FUNDS: ACQUIRED!
Cost: $6,250.00
CONSTRUCTION: COMPLETED!
Nov/20/2023 - Nov/25/2023




10 Acre Land
Gilchrist County Florida
Acquired Land for Building Site