EVENTS

Updated periodically, this Events Page showcases specific projects of our Building Campaign, both ongoing and completed works. We post each project's estimated funds needed, expected time of construction dates, status updates, and additional donation opportunities for our Building Fund.

Future Construction Coming Soon! Donate Now to help us build for the Greater Glory of God!

Engineering, Development, and Permitting

Funds: NEEDED!

ESTIMATED COST: $24,500

STATUS: In Progress - 58% of Goal met

DATES: June 2025 - TBA

 

Site Development Engineering and Permitting Phase will be completed with plans and specifications being submitted to the Gilchrist County Community Development Planning and Zoning Department. These Site Development Plans will include all the necessary planning, zoning and site engineering requirements, under Gilchrist County's Preliminary and Final Site Plan approval process. We are currently engaging a site engineer to prepare these plans. The anticipated cost and schedule for this work is ~$25,000 with an expected 8-month process to receive an approved site permit.  

Site Prep
Architectural Design

Funds: ACQUIRED!

STATUS: COMPLETED

DATES: Feb 2025 - May 2025

​

​Our full Conceptual Design, with a Preliminary Building Construction matrix has been completed by Baker Architects', Lafayette, Co. In addition to providing the necessary Architectural floor plans and building elevations, Baker Architect's has provided us with three-dimensional (3-D) modeling of the building interior and exterior spaces, as well site plan overviews.

Back Property Fence

FUNDS: ACQUIRED!

COST: $3,328.84

CONSTRUCTION STATUS: COMPLETED

DATES: Oct/4/2024 - Oct/8/2024

Site Prep
Land Surveying

FUNDS: ACQUIRED!

Project claimed by Anonymous Donor!

COST: $1,854

CONSTRUCTION STATUS: COMPLETED

DATES: Aug/14/2024

Site Prep
Land Clearing For Monastery

FUNDS: ACQUIRED!

COST: $9,000

CONSTRUCTION STATUS: COMPLETED

DATES: May/11/2024 - May/16/2024

Front Property Fence

FUNDS: ACQUIRED!

Cost: $4,511.42

CONSTRUCTION: COMPLETED!

Dec/29/2023 - Dec/31/2023

Driveway Access 
Front Clearing

FUNDS: ACQUIRED!

Cost: $6,250.00

CONSTRUCTION: COMPLETED!

Nov/20/2023 - Nov/25/2023

10 Acre Land
Gilchrist County Florida

Acquired Land for Building Site

ABOUT US

To the extent permitted by 26 U.S.C. § 501(c)(3), Habit Forming Sisters Corporation is a Building Fund Project for the construction of a Traditional Carmelite Monastery in High Springs, Florida for the greater glory of God, the salvation of souls, and the safekeeping of the Traditional Latin Mass.

ADDRESS

Habit Forming Sisters

PO Box 564

Richmond Hill, GA 31324

  • Facebook
  • Etsy

Subscribe to get project updates

Thank you for subscribing!

© 2023 HABIT FORMING SISTERS CORPORATION. Powered and secured by Wix

bottom of page